Application Registered:
Comments Welcome By:
08/04/2017
Application Decided:
31/01/2018

Subscription Request Sent :

Error :

Type:
Outline Planning Permission
Location:
92 Main Road, West Huntspill, Highbridge, TA9 3QZ
Proposal:
Outline planning permission for residential development on site of existing public house (to be demolished).
Case Officer:
Shanta Parsons
Registered Date:
22/02/2017
Applicant:
British Country Inns 2 plc
Applicant Address:
Hyde Park House 5 Manfred Road London SW152RS
Agent:
PMBC, 11 Burlington Road
Agent Address:
11 Burlington Road Redland Bristol BS56 6TJ
Consultation Start Date:
20/04/2017
Earliest Decision Date:
08/04/2017
Committee Date:
09/05/2017
Decision Level:
Committee
Decision:
Granted Permission
Decision Date:
31/01/2018

Conditions and Reasons

Number
Condition
Complied Date
1
Approval of the details of the access, appearance, landscaping, layout and scale (hereinafter called "the reserved matters") shall be obtained from the local planning authority in writing before any development is commenced. Plans and particulars of the reserved matters referred to above, relating to the access, appearance, landscaping, layout and scale, shall be submitted in writing to the local planning authority and shall be carried out as approved. Application for approval of the reserved matters shall be made to the local planning authority before the expiration of three years from the date of this permission. The development hereby permitted shall be begun before the expiration of two years from the date of approval of the last of the reserved matters to be approved, whichever is the later. Reasons: The application was submitted as an outline application in accordance with the provisions of Article 5(1) of the Town and Country Planning (Development Management Procedure) Order 2015. In accordance with the provisions of Section 92 of the Town and Country Planning Act, 1990 (As amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2
The development hereby permitted shall be carried out in accordance with the approved plans listed in schedule A. Reason: For the avoidance of doubt and in the interests of proper planning.
3
The site of the proposed development may be contaminated.  Therefore unless otherwise agreed by the Local Planning Authority, development other than that required to be carried out as part of an approved scheme of remediation must not commence until conditions A to C have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition D has been complied with in relation to that contamination. A. Site Characterisation A detailed site investigation and risk assessment must be completed in accordance with current UK guidance to assess the nature, extent and scale of any contamination on the site, whether or not it originates on the site. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The investigations, risk assessments and written reports must be approved in writing by the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) desk study information, conceptual models, investigation methods, investigation results and interpretation and any other information required by the local planning authority to justify and appraise the report findings. (iii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iv) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with current UK guidance including DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11'. B. Submission of Remediation Scheme In cases where contamination is shown to exist a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property, the natural and historical environment and surrounding land must be prepared, and approved in writing by the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. C. Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and approved in writing by the local planning authority. D. Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of condition A, and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of condition B, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority in accordance with condition C. E. Long Term Monitoring and Maintenance If a monitoring and maintenance scheme, to include monitoring the long-term effectiveness of the proposed remediation, is required as part of the approved remediation scheme then the monitoring and maintenance scheme will need to be approved in writing by the local planning authority. Following completion of the measures identified in that monitoring and maintenance scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority for approval. This must be conducted in accordance with current UK guidance including DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11'. Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
4
Prior to the commencement of development,  including any site clearance, groundworks or construction within each sub-phase (save such preliminary or minor works that the Local Planning Authority may agree in writing), a Construction Management Plan (CMP) to manage the impacts of construction during the life of the works, shall be submitted to and approved in writing by the Local Planning Authority. For the avoidance of doubt, the CMP shall, amongst other things, include:-   a)     measures to regulate the routing of construction traffic; b)     the importation and of spoil and soil on site; c)     the removal /disposal of materials from site, including soil and vegetation; d)     the location and covering of stockpiles; e)     details of measures to prevent mud from vehicles leaving the site and must include wheel-washing facilities; f)     control of fugitive dust from earthworks and construction activities; dust suppression; g)    a noise control plan (which includes control methods) h) a waste disposal policy; i)     details of any site construction office, compound and ancillary facility buildings; j)     specified on-site parking for vehicles associated with the construction works and the provision made for access thereto; k) a point of contact (such as a Construction Liaison Officer/site manager) and details of how complaints will be addressed, including an appropriate phone number. The details so approved and any subsequent amendments as shall be agreed in writing by the Local Planning Authority shall be complied with in full and monitored by the applicants to ensure continuing compliance during the construction of the development. Reason: To protect the amenity of local residents from potential impacts whilst site clearance, groundworks and construction is underway.
5
No demolition, or construction work involving noisy activities (such as the use of power tools/hammering) or deliveries to and from the site shall take place outside the hours of 07:00 to 18:00 Mondays to Fridays, 08:00 to 13:00 on Saturdays, with the exception of specific works which shall have been agreed in advance and in writing by the local planning authority and shall include details of the task, the date and duration of works. No works to take place on Sundays and Bank Holidays.   Reason: To protect the amenity of local residents from potential impacts whilst site clearance, groundworks and construction is underway.
6
No development approved by this permission shall be commenced until a scheme for the provision of surface water drainage works has been submitted to and approved in writing by the Local Planning Authority. The drainage works shall be completed in accordance with the details and timetable agreed prior to the first occupation of any of the dwellings. Reason: To prevent increased risk of flooding by ensuring the provision of a satisfactory means of surface water disposal.
7
The proposed roads, including footpaths and turning spaces where applicable, shall be constructed in such a manner as to ensure that each dwelling before it is occupied shall be served by a properly consolidated and surfaced footpath and carriageway, to at least base level, between the dwelling and existing highway. Reason: In the interests of highway safety.
8
No development approved by this planning permission shall take place until such time as a scheme detailing flood resilience measures to be incorporated into the construction of the proposed dwellings has been submitted to, and approved in writing by, the local planning authority.   The scheme shall be fully implemented and subsequently maintained, in accordance with the approved details.   Reason: To reduce the risk of flooding to the proposed development and future users.
9
Prior to the first occupation of any of the dwellings hereby approved a flood evacuation plan will be submitted to and approved in writing with the Local Planning Authority including details of any early warning systems and rescue/evacuation routes. The development shall be carried out in accordance with the approved details unless otherwise agreed in writing. Reason: To reduce the risk to future users.
10
All finished floor levels should be set at least 500mm above local ground levels, unless otherwise agreed in writing. Reason: To protect the development from localised flooding, or a breach in the sea defences
11
The proposed estate roads, footways, footpaths, tactile paving, cycleways, bus stops/bus lay-bys, verges, junctions, street lighting, sewers, drains, retaining walls, service routes, surface water outfall, vehicle overhang margins, embankments, visibility splays, accesses, carriageway gradients, drive gradients, car, motorcycle and cycle parking, and street furniture shall be constructed and laid out in accordance with details to be approved by the Local Planning Authority in writing before their construction begins. For this purpose, plans and sections, indicating as appropriate, the design, layout, levels, gradients, materials and method of construction shall be submitted to the Local Planning Authority. Reason: In the interests of highway safety and visual amenity.
12
There shall be no obstruction to visibility greater than 300 millimetres above adjoining road level in advance of lines drawn 2.4 metres back from the carriageway edge on the centre line of the access and extending to points on the nearside carriageway edge 39m to the north, and 43m to the south of the access. Such visibility shall be fully provided before the first dwelling of the development hereby permitted is occupied and shall thereafter be maintained at all times. Reason In the interests of highway safety.
13
No work shall commence on the development site until an appropriate right of discharge for surface water has been obtained before being submitted to and approved in writing by the Local Planning Authority. A drainage scheme for the site showing details of gullies, connections, soakaways and means of attenuation on site shall be submitted to and approved in writing by the Local Planning Authority. The drainage works shall be carried out in accordance with the approved details, unless otherwise agreed in writing with the Local Planning Authority. Reason:In the interest of highway safety.
14
Any dwelling entrance gates erected shall be hung to open inwards, and shall thereafter be maintained in that condition at all times. Reason: In the interest of highway safety.
15
Before any part of the development hereby permitted is first occupied, a 2.0m wide (minimum) footway shall be constructed over the entire frontage of the site in accordance with a specification to be approved in writing by the Local Planning Authority. Such works to be the subject of a suitable legal agreement (e.g. Section 278). Reason: In the interest of highway safety.
16
Plans showing a parking area providing for an agreed number of vehicles shall be submitted to and approved in writing by the Local Planning Authority before the development is commenced. This area shall be properly consolidated before the dwellings are occupied and shall not be used other than for the parking of vehicles in connection with the development hereby permitted. Reason: In the interest of highway safety.

Copyright Warning

Plans, drawing and material submitted to the council are protected by the copyright acts (Section 47, 1988 Act). You may only use the documents listed below for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Copies must not be made without the prior permission of the copyright owner. By viewing the documents listed below you are accepting this copyright.

Please note: Documents held in our archival system may not meet current accessibility requirements. Many of these documents are exempt from these requirements. See Accessible documents at Somerset Council for further information.

4 Documents Found
Document Type Description Uri RenditionUri Registered Date File Size Extension
6 Documents Found
Filesize:  3.74 MB
Document Type Description Uri RenditionUri Registered Date File Size Extension
8 Documents Found
Filesize:  4.48 MB
Document Type Description Uri RenditionUri Consultee Registered Date File Size Extension
8 Documents Found
Filesize:  682 kb
Document Type Description Uri RenditionUri Registered Date File Size Extension
2 Documents Found
Filesize:  1.01 MB
Document Type Description Uri RenditionUri Registered Date File Size Extension
1 Documents Found
Document Type Description Uri RenditionUri Registered Date File Size Extension

Please note: Documents held in our archival system may not meet current accessibility requirements. Many of these documents are exempt from these requirements. See Accessible documents at Somerset Council for further information.

No Committee documents found.