  • Application Number: 08/24/00047
  • Parish/Town Council:

Application Progress:

The box that is highlighted in dark green shows how the application is progressing. If the "Comments Welcome By" box is highlighted you can make a comment about the application.

Application Registered:
Comments Welcome By:
22/05/2024
Application Decided:
21/06/2024

Subscription Request Sent :

Error :

Type:
Full Planning Permission
Location:
3 Blake Street, Bridgwater, Somerset
Proposal:
Erection of a building containing 1no. one-bed flat, 1no. two-bed flat and 2no. commercial/retail units, on site of existing (to be demolished).
Case Officer:
Liam Evans
Registered Date:
16/04/2024
Applicant:
Axeus Homes Ltd
Applicant Address:
West View Bath Road Horsey Bridgwater TA7 8PF
Agent:
Jackson Architects Ltd, 51 School Road
Agent Address:
51 School Road Charlton Kings Cheltenham GL53 8BP
Consultation Start Date:
18/04/2024
Earliest Decision Date:
22/05/2024
Decision Level:
Delegated
Decision:
Granted Permission
Decision Date:
21/06/2024

Conditions and Reasons

Number
Condition
Complied Date
1
The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: In accordance with the provisions of Section 91 of the Town and Country Planning Act, 1990 ( as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2
The development hereby permitted shall be carried out in accordance with the approved plans listed in schedule A. Reason: For the avoidance of doubt and in the interests of proper planning.
3
The development hereby permitted must not be occupied or utilised until a scheme showing details of the proposed cycle parking facilities at a rate of 1 space per bedroom is submitted to the Local Planning Authority. Any such scheme shall be constructed before the development is occupied and maintained thereafter. Reason: To encourage sustainable forms of travel.
4
If any unforeseen contamination is found during excavations, the Local Planning Authority shall be notified immediately. Where remediation is deemed necessary by the Local Planning Authority, a remediation scheme shall be submitted to and approved in writing by the Local Planning Authority and then implemented in accordance with the submitted details. Reason: To ensure that the land is suitable for the intended uses and to ensure that the development can be carried out safely without unacceptable risks to human health, controlled waters and other receptors both onsite and offsite, in accordance with Policy D24 of the Sedgemoor Local Plan.
5
No development shall commence, including site clearance, groundworks or construction, unless a Construction Environmental Management Plan (CEMP) to manage the impacts of construction during the life of the works, has been submitted to and approved in writing by the Local Planning Authority. For the avoidance of doubt, the CEMP shall, amongst other things, include:- a)Measures to regulate the on-site routing of construction traffic; b)The importation of spoil and soil on site; c)The removal /disposal of materials from site, including soil and vegetation; d)The location and covering of stockpiles; e)Details of measures to prevent mud from vehicles leaving the site and must include wheel- washing facilities; f)Control of fugitive dust from earthworks and construction activities; dust suppression measures; g)Noise and Vibration control plan (which includes control methods) to include mitigation measures as defined in BS 5528: Parts 1 and 2: 2009 'Code of practice for noise and vibration control on construction and open sites' shall be used to minimise noise or vibration disturbance from construction works; h)A waste disposal policy (to include no burning on site); i)Measures for controlling the use of site lighting whether required for safe working or for security purposes; j)Details of any site construction office, compound and ancillary facility buildings; k)Specified on-site parking for vehicles associated with the construction works and the provision made for access thereto; l)A point of contact (such as a Construction Liaison Officer/site manager) and details of how complaints will be addressed, including an appropriate phone number. m) Prevention of nuisance caused by radios, alarms, PA systems or raised voices And shall confirm: That noise generating activities shall not occur outside of the following hours: •Mon - Fri 08:00-18:00 •Sat 08:00 -13:00 •All other times, including Sundays, Bank and Public Holidays there shall be no such noise generating activities. The details so approved and any subsequent amendments as shall be agreed in writing by the Local Planning Authority shall be complied with in full and monitored by the applicants to ensure continuing compliance during the construction of the development. Reason: A pre-commencement condition to ensure that safe operation of the highway and minimise the effect of noise, odour and dust from the construction phase of development on occupiers of nearby properties in the interests of residential amenity and sustainable development, in accordance with Policies D24 and D25 of the Sedgemoor Local Plan.
6
Before the commencement of the development hereby permitted the applicant, or their agents or successors in title, shall have secured the implementation of a programme of archaeological work in accordance with a Written Scheme of Investigation (WSI) which has been submitted and approved in writing by the Planning Authority. The WSI shall include details of the archaeological excavation, the recording of the heritage asset, the analysis of evidence recovered from the site and publication of the results. The development hereby permitted shall be carried out in accordance with the approved scheme. Reason: A pre-commencement condition as the site lies within the medieval town and port of Bridgwater founded in c.1200 AD and the proposal has the potential to impact on remains relating to the medieval town.
7
No work shall commence in the removal of the existing tin workshop until the structure has been recorded and the destination of the tin workshop and the next phase of use has been submitted to and agreed in writing with the Local Planning Authority. Reason: A pre-commencement condition in order to ensure that the works preserve the special architectural and historic interest of the listed building.
8
Before the windows and doors hereby approved are installed, details of their material, design, specification, method of opening, method of fixing and finish, in the form of drawings and sections of no less than 1:20 scale, shall be submitted to and agreed in writing by the Local Planning Authority. The works shall be carried out only in accordance with the agreed window and door details. Reason: In order to ensure that the works preserve the special architectural and historic interest of the listed building.
9
Before any bricks are laid or roof is installed, samples or detailed specifications of all external materials to be used on the works hereby granted consent shall be submitted to and agreed in writing by the Local Planning Authority. The works shall be carried out only in accordance with the agreed materials. Reason: To preserve the special architectural and historic interest of the listed building.
10
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re- enacting that Order) (with or without modification), no windows/dormer windows other than those expressly authorised by this permission shall be constructed. Reason: In the interests of residential amenity and privacy.
11
The ground floor commercial units shall be used falling within Class E use only. Reason: For the avoidance of doubt as to the extent of the planning permission.

Copyright Warning

Plans, drawing and material submitted to the council are protected by the copyright acts (Section 47, 1988 Act). You may only use the documents listed below for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Copies must not be made without the prior permission of the copyright owner. By viewing the documents listed below you are accepting this copyright.

Please note: Documents held in our archival system may not meet current accessibility requirements. Many of these documents are exempt from these requirements. See Accessible documents at Somerset Council for further information.

4 Documents Found
Filesize:  15.66 MB
Document Type Description Uri RenditionUri Registered Date File Size Extension
2 Documents Found
Filesize:  370 kb
Document Type Description Uri RenditionUri Registered Date File Size Extension
7 Documents Found
Filesize:  3.45 MB
Document Type Description Uri RenditionUri Consultee Registered Date File Size Extension
3 Documents Found
Filesize:  9.18 MB
Document Type Description Uri RenditionUri Registered Date File Size Extension
2 Documents Found
Filesize:  4.14 MB
Document Type Description Uri RenditionUri Registered Date File Size Extension

Please note: Documents held in our archival system may not meet current accessibility requirements. Many of these documents are exempt from these requirements. See Accessible documents at Somerset Council for further information.

No Committee documents found.