Application Details

Click to return to the planning register search page.
  • Application Number: 08/16/00009
  • Parish/Town Council:

Application Progress:

The box that is highlighted in dark green shows how the application is progressing. If the "Comments Welcome By" box is highlighted you can make a comment about the application.

Application Registered:
Comments Welcome By:
12/03/2016
Application Decided:
08/11/2016

Subscription Request Sent :

Error :

Type:
Full Planning Permission
Location:
Former Bridgwater Community Hospital (2), Salmon Parade, Bridgwater, TA6 5AH
Proposal:
Proposed redevelopment of the former Bridgwater Hospital to include the change of use and conversion of three storey Hospital building to Hotel (Class C1), former Physiotherapy Building to Day Nursery (Class D1), change of use, conversion and extension of former Dental Surgery to three dwellings (Class C3) and ground floor Restaurant (Class A3), erection of three storey Health Club/Gym/Swimming Pool (Class D2) on the site of single storey outpatient building (to be demolished) and demolition of first floor glazed room over porch fronting Salmon Parade.
Case Officer:
Jeremy Ebdon
Registered Date:
05/02/2016
Applicant:
Salmon Parade Developments Ltd & NHS Property Services Limited (NHSPS)
Applicant Address:
Cygnet House 14b High Street Wells Somerset BA5 2SG
Agent:
Collier Reading Architects
Agent Address:
Coach House Studio 34a Chamberlain Street Wells Somerset BA5 2PJ
Consultation Start Date:
09/02/2016
Earliest Decision Date:
12/03/2016
Decision Level:
Delegated
Decision:
Granted Permission
Decision Date:
08/11/2016

Conditions and Reasons

Number
Condition
Complied Date
1
The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: In accordance with the provisions of Section 91 of the Town and Country Planning Act, 1990 ( as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2
The development hereby permitted shall be carried out in accordance with the approved plans listed in schedule A. Reason: For the avoidance of doubt and in the interests of proper planning.
3
No development shall be commenced until details of the surface water drainage scheme based on sustainable drainage principles together with a programme of implementation and maintenance for the lifetime of the development have been submitted to and approved in writing by the Local Planning Authority. The drainage strategy shall ensure that surface water runoff post development is attenuated on site and discharged to allow for a 30% betterment on existing runoff rates and volumes. Such works shall be carried out in accordance with the approved details. These details shall include: - Details of phasing (where appropriate) and information of maintenance of drainage systems during construction of this and any other subsequent phases. Information about the design storm period and intensity, discharge rates and volumes (both pre and post development), temporary storage facilities, means of access for maintenance (6 metres minimum), the methods employed to delay and control surface water discharged from the site, and the measures taken to prevent flooding and pollution of the receiving groundwater and/or surface waters. Any works required off site to ensure adequate discharge of surface water without causing flooding or pollution (which should include refurbishment of existing culverts and headwalls or removal of unused culverts where relevant). Flood water exceedance routes both on and off site, note, no part of the site must be allowed to flood during any storm up to and including the 1 in 30 event, flooding during storm events in excess of this including the 1 in 100yr (plus 30% allowance for climate change) must be controlled within the designed exceedance routes demonstrated to prevent flooding or damage to properties. A management and maintenance plan for the lifetime of the development which shall include the arrangements for adoption by an appropriate public body or statutory undertaker, management company or maintenance by a Residents' Management Company and / or any other arrangements to secure the operation and maintenance to an approved standard and working condition throughout the lifetime of the development Reason: To ensure that the development is served by a satisfactory system of surface water drainage and that the approved system is retained, managed and maintained in accordance with the approved details throughout the lifetime of the development, in accordance with paragraph 17 and sections 10 and 11 of the National Planning Policy Framework, Paragraph 103 of the National Planning Policy Framework and the Technical Guidance to the National Planning Policy Framework (March 2015). This is a pre-commencement condition because drainage works typically need to be installed at the first stages of development.
4
No development shall commence unless a Construction Environmental Management Plan has been submitted to and approved in writing by the Local Planning Authority. The works shall be carried out strictly in accordance with the approved plan. The plan shall include: Construction vehicle movements; Construction operation hours; Construction vehicular routes to and from site; Construction delivery hours; Expected number of construction vehicles per day; Car parking for contractors; Specific measures to be adopted to mitigate construction impacts in pursuance of the Environmental Code of Construction Practice; A scheme to encourage the use of Public Transport amongst contactors; and Measures to avoid traffic congestion impacting upon the Strategic Road Network. Reason: In the interests of the safety and convenience of all users of the highway. This is a pre-commencement condition because it governs how construction will be carried out once development starts.
5
The area allocated for parking and turning on the submitted plan shall be kept clear of obstruction at all times and shall not be used other than for the parking of vehicles in connection with the development hereby permitted. Reason: In the interests of the safety and convenience of all users of the highway.
6
No building shall be first occupied or otherwise used for any purpose until provision has been made within the site for the loading and unloading of goods vehicles in accordance with the approved plans. Reason: In the interests of the safety and convenience of all users of the highway.
7
Prior to first occupation or first use of the development hereby permitted, spaces for staff and visitors' bicycles and parking for motorcycles shall be laid out, constructed and drained in accordance with a detailed scheme to be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the safety and convenience of all users of the highway.
8
Prior to the commencement of development a written commitment to the sourcing of local labour shall be submitted to and approved in writing by the local planning authority. The written commitment, as a minimum, shall set out the following matters: i) The proportion of construction workers whom will be sourced from the local labour pool; ii) The proportion of subsequent staff employed in the development whom will be sourced from the local labour pool; iii) Work experience/ apprenticeship opportunities; iv) The proportion of local procurement and sourcing; v) On-going skills development and training opportunities; vi) The steps that will be taken to ensure that the above is implemented; vii) The operator shall maintain a record of i - vi above and shall make that information available to the local planning authority at all reasonable times upon request. Reason: In accordance with policy D11 of the Sedgemoor Core Strategy (2006-2027). This matter needs to be agreed prior to commencement in order to ensure that local labour is used in the project from the start. This is a pre-commencement condition because a proportion of local labour needs to be agreed before workers are first employed on site.
9
During the following times in the demolition/construction phase no machinery shall be operated, no process shall be carried out apart from internal fittings only and no deliveries can be taken at or dispatched from the site outside the following times: a) Monday - Friday 08.00 - 18.00, b) Saturday 09.00 - 13.00 c) nor at any time on Sunday, Bank or Public holidays. Reason: To protect the amenity of local residents.
10
Any external lighting must only directly illuminate the application site. Reason: To safeguard residents from obtrusive light.
11
An adequate water supply shall be provided on site and maintained at all times. Where necessary or at the direction of the Local Authority, it shall be used to provide adequate dust suppression and minimise fugitive dust emissions from the development site. Reason: To safeguard local residents from dust nuisance.
12
There shall be no burning of waste on the site during any construction or demolitions works. Reason: To safeguard local residents from smoke nuisance.
13
The site of the proposed development may be contaminated.  Therefore unless otherwise agreed by the Local Planning Authority, development other than that required to be carried out as part of an approved scheme of remediation must not commence until conditions A to C have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition D has been complied with in relation to that contamination. Site Characterisation A detailed site investigation and risk assessment must be completed in accordance with current UK guidance to assess the nature, extent and scale of any contamination on the site, whether or not it originates on the site. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The investigations, risk assessments and written reports must be approved in writing by the Local Planning Authority. The report of the findings must include: a survey of the extent, scale and nature of contamination; desk study information, conceptual models, investigation methods, investigation results and interpretation and any other information required by the local planning authority to justify and appraise the report findings. an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iv) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with current UK guidance including DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11'. Submission of Remediation Scheme In cases where contamination is shown to exist a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property, the natural and historical environment and surrounding land must be prepared, and approved in writing by the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and approved in writing by the local planning authority. Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of condition A, and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of condition B, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority in accordance with condition C. Long Term Monitoring and Maintenance If a monitoring and maintenance scheme, to include monitoring the long-term effectiveness of the proposed remediation, is required as part of the approved remediation scheme then the monitoring and maintenance scheme will need to be approved in writing by the local planning authority. Following completion of the measures identified in that monitoring and maintenance scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority for approval. This must be conducted in accordance with current UK guidance including DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11'. Reason: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
14
No system of public address, loudspeaker system or amplified music shall be operated within the site, unless details of such facilities have previously been submitted to, and approved in writing by, the local planning authority, pursuant to this condition. Reason: To safeguard local residents from noise and disturbance.
15
No flues or extraction systems shall be installed in relation to the commercial kitchens unless details have previously been submitted to, and approved in writing by, the local planning authority, pursuant to this condition. Reason: In the interests of the amenity of nearby residential properties.
16
Prior to the commencement of the development hereby approved, material palettes with representative samples for the proposed hotel lift shaft cladding, proposed restaurant, proposed gym/health club, proposed day nursery shall be submitted to, and approved in writing by, the Local Planning Authority. The development shall proceed in accordance with the approved materials/details. Reason:To safeguard the character, appearance and significance of the listed buildings and in accordance with policy D17 of the Sedgemoor District Council Core Strategy and also in the interests of the character and appearance of the development. This is a pre-commencement condition because materials need to be agreed early to avoid abortive costs in ordering unacceptable materials.
17
Prior to the commencement of the development hereby approved, full details of hard and soft landscape works, including an implementation and management plan, have been submitted to and approved in writing by the local planning authority. Details of soft landscape works shall include retention of any existing trees; finished levels/contours; planting plans; written specifications (including cultivation and other operations associated with plant and grass establishment); schedules of plants, noting species, plant sizes and proposed numbers/densities where appropriate. The hard landscape works shall include means of enclosure; boundary and surface treatments; structures (furniture, play equipment, refuse and other storage units; signs and lighting). All works shall be carried out in accordance with the approved details and the implementation plan and thereafter maintained in accordance with the approved management plan. Reason: To secure a landscape scheme that will complement the development in the interests of visual amenity and the setting of the listed buildings. This is a pre-commencement condition as it involves the retention of trees, which needs to be secured before development which might damage then starts.
18
The development shall not be carried out otherwise than in strict accordance with an External Lighting Scheme, including an implementation programme, which shall be submitted to and approved in writing by the local planning authority prior to the installation of any external lighting. Reason: To safeguard the character, appearance and significance of the listed buildings and in accordance with policy D17 of the Sedgemoor District Council Core Strategy and also in the interests of the character and appearance of the development.

Copyright Warning

Plans, drawing and material submitted to the council are protected by the copyright acts (Section 47, 1988 Act). You may only use the documents listed below for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Copies must not be made without the prior permission of the copyright owner. By viewing the documents listed below you are accepting this copyright.

Please note: Documents held in our archival system may not meet current accessibility requirements. Many of these documents are exempt from these requirements. See Accessible documents at Somerset Council for further information.

8 Documents Found
Document Type Description Uri RenditionUri Registered Date File Size Extension
49 Documents Found
Filesize:  101.71 MB
Document Type Description Uri RenditionUri Registered Date File Size Extension
13 Documents Found
Filesize:  8.06 MB
Document Type Description Uri RenditionUri Consultee Registered Date File Size Extension
1 Documents Found
Filesize:  15 kb
Document Type Description Uri RenditionUri Registered Date File Size Extension
2 Documents Found
Filesize:  185 kb
Document Type Description Uri RenditionUri Registered Date File Size Extension

Please note: Documents held in our archival system may not meet current accessibility requirements. Many of these documents are exempt from these requirements. See Accessible documents at Somerset Council for further information.

No Committee documents found.